Final report out cleaning and backfilling of the 30-inch

Final report out cleaning and backfilling of the 30-inch To Akakus Oil Operation Company Route of the line from O to 87 kmNote that this well is not mentioned in the list of wells to Contracted and that it were cleaned at the request of Engineer Samir Dzliter.

Date:- 08/01/2024

1.

Carrying out Cadastral lifting of the route of the freight line from O to 87 km,

determining the buried parts of it.

Done

 

2.

Inspection and maintenance of vehicles and mechanisms used

Done

 

3.

Drilling of corroded counters, cleaning and covering the surface

Done

 

4.

Clean the terminals and remove dust around the valves

Done

 

5.

Leveling and backfilling the line path using a bulldozer

Done

 

6.

Collection and disposal of garbage and all waste

Done

 

7.

Mixing the SC823 material and spraying the soil a path from O to 87 km with a

width of 5 meters from two sides

Done