Final report out cleaning and backfilling of the 30-inch To Akakus Oil Operation Company Route of the line from O to 87 kmNote that this well is not mentioned in the list of wells to Contracted and that it were cleaned at the request of Engineer Samir Dzliter.
Date:- 08/01/2024
1. |
Carrying out Cadastral lifting of the route of the freight line from O to 87 km, determining the buried parts of it. |
Done |
|
2. |
Inspection and maintenance of vehicles and mechanisms used |
Done |
|
3. |
Drilling of corroded counters, cleaning and covering the surface |
Done |
|
4. |
Clean the terminals and remove dust around the valves |
Done |
|
5. |
Leveling and backfilling the line path using a bulldozer |
Done |
|
6. |
Collection and disposal of garbage and all waste |
Done |
|
7. |
Mixing the SC823 material and spraying the soil a path from O to 87 km with a width of 5 meters from two sides |
Done |